Shanti Prime Publication Pvt. Ltd.
Levy of GST — After the GST comes into force, the works contract is no longer divisible into a contract for the supply of goods and a service contract. It is a service contract and the entire unadjusted mobilisation advance as on 01/07/2017, according to the Contract, applies towards payment of consideration for the works contract service. The Applicant is deemed to have supplied works contract service to KMRCL on 01/07/2017 to the extent covered by the lump-sum that stood credited to its account on that date as mobilisation advance and GST is leviable thereon accordingly. Thus, the value of the supply of works contract service in the subsequent invoices as and when raised should, therefore, be reduced to the extent of the advance adjusted in such invoices. The GST should, therefore, be charged on the net amount that remains after such adjustment. — Siemens Ltd., In Re… [2019] 15 TAXLOK.COM 051 (AAR-WB)